Getting a new electricity connection in Sargodha District? This guide covers the complete process from application to meter installation.
Apply at your local FESCO subdivision office with CNIC, property documents, and application fee (Rs. 500-2000 depending on load). Processing takes 15-30 days for domestic connections.
Estimated Time: 15-30 days for domestic connections
Estimated Cost: Rs. 8,000 - 50,000 depending on connection type and load
- Original CNIC + 2 photocopies
- Property ownership documents (Registry/Fard/Intiqal)
- Affidavit on Rs. 50 stamp paper
- 4 passport size photographs
- NOC from landlord (if rented property)
- Site map showing nearest FESCO transformer
- Proof of internal wiring completion
Step-by-Step Guide
Domestic (A-1): For residential use. Commercial (A-2): For shops/offices. Industrial (B-1, B-2): For factories. Agricultural (Tubewell): For farming. Each has different tariffs and requirements.
Pro Tip: Choose carefully - changing connection type later requires a new application and fees.
Single Phase: Up to 5 kW (most homes). Three Phase: 5-500 kW (large homes, shops, industries). List all your planned appliances and their wattage to determine required load.
Original CNIC + 2 copies. Property ownership proof (Registry/Fard). Affidavit on stamp paper (Rs. 50). Passport size photos (4 copies). NOC from landlord (if rented). Site map showing nearest transformer.
Pro Tip: Get the affidavit from a Notary Public near Katchery. Cost: Rs. 200-300.
Visit your subdivision office during working hours (8 AM - 2 PM). Submit form with all documents. Pay application fee (Rs. 500 domestic, Rs. 1000 commercial, Rs. 2000 industrial).
FESCO lineman will visit your location within 7-10 days to verify the site, check transformer availability, and assess wiring requirements. Be present during inspection.
Pro Tip: Ensure your internal wiring is complete before inspection. FESCO won't connect without proper wiring.
After approval, pay the demand notice amount at any designated bank. Domestic single-phase: Rs. 5,000-15,000. Commercial: Rs. 15,000-50,000. Industrial: Rs. 50,000+. Keep the receipt.
Within 7-14 days of payment, FESCO will install your meter. They'll provide a reference number and first bill. Verify meter reading is zero at installation.
Common Mistakes to Avoid
Applying without complete property documents
Get your property papers in order first. Visit Tehsil office for Fard if needed.
Underestimating load requirement
Always apply for slightly more load than current needs. Upgrading later costs more than initial higher load.
Not getting internal wiring done before application
FESCO requires complete wiring for inspection. Hire a licensed electrician to wire your premises first.
Paying to unauthorized agents
Only pay at FESCO office or designated banks. Get official receipts for every payment.
Frequently Asked Questions
Domestic: 15-30 days. Commercial: 20-45 days. Industrial: 30-90 days (depending on load and transformer availability).
Total cost including application fee, security deposit, and connection charges: Rs. 8,000-20,000 for single phase, Rs. 25,000-50,000 for three phase.
Partial online application is available at fesco.com.pk, but you still need to visit the office for document verification and payment.
You may need to share the cost of a new transformer with neighbors, or wait until FESCO installs one. Contact the SDO for options.
Important Contacts
FESCO Customer Service
118
24/7
ENC Portal Helpdesk
042-99205316
9 AM - 5 PM
Sargodha City SDO Office
048-3724590
8 AM - 2 PM